RFP 1-13-C026: East Building Life Safety Renovations, Dulles Airport

PROJECT OVERVIEW
|
RFP Issue Date: December 10, 2012
Deadline for Proposals: 2:00 PM (Eastern), January 22, 2013
Pre-Proposal Conference: 10:00 AM (Eastern), December 20, 2012 at 4th Floor Conference Room #1, 45025 Aviation Drive, Dulles Airport
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: $250,000 - $500,000
Project Duration: 90 days from Notice to Proceed
Bond Requirements: 100% Payment, 100% Performance
Project Summary:
The Contractor shall furnish all necessary labor, materials, tools, equipment, and supervision to perform miscellaneous life safety renovations at the East Building at Washington Dulles International Airport to include, at a minimum, installation of stairwell gates, new panic bar hardware and ADA signage in stairwells.
LDBE Requirement:
This RFP has a 100% Local Disadvantaged Business Enterprise (LDBE) participation requirement and a 50% Voluntary MBE/WBE goal. Firms located within a 100-mile radius and whose 3 year average gross receipts, including all affiliates, do not exceed the size standard(s) below are eligible for consideration. For more LDBE/MBE/WBE information, including other LDBE size standards, contact the Equal Opportunity Programs Department at 703-417-8625.
LDBE Size Standards:
NAICS Code Type of Work / Service LDBE Size Standard
236220 Commercial & Institutional Building Contractors $33.5 Million
238210 Electrical Contractors $14.0 Million
238220 Plumbing, Heating, A/C, Ventilation Contractors $14.0 Million
Amendments Issued:
None
Last Updated January 9, 2013