RFP 1-13-C034: Window Wall Rehabilitation, Main Terminal, Dulles Airport

PROJECT OVERVIEW
|
RFP Issue Date: January 10, 2013
Deadline for Proposals: 2:00 PM (Eastern), February 14, 2013
Pre-Proposal Conference: 10:00 AM (Eastern), January 16, 2013 at Third Floor Conference Room B, 45045 Aviation Drive, Dulles Airport
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Estimated Dollar Value: $250,000 - $500,000
Project Duration: 180 days from Notice to Proceed
Bond Requirements: 100% Payment, 100% Performance
Project Summary:
The Contractor shall furnish all necessary labor, materials, tools, equipment, and supervision to rehabilitate the top joints of the east and west window bays (32 total) on the airside and landside of the Main Terminal at Washington Dulles International Airport. The project consists of repairs of the flexible seals and flashing at the top header of the window walls including cleaning of adjacent plasterwork. It also includes repairs of expansion joint and soffit of the exterior portion of roof at the east and west ends of terminal. The work requires phasing to maintain landside pedestrian traffic.
LDBE Requirement:
None
Amendments Issued:
One, February 1, 2013.  The due date for proposals remains unchanged.
CLICK HERE to download Amendment Documents