RFQ 8-13-P029: Point-to-Point T-1 Circuits for DCMP Phase 2 Offices

PROJECT OVERVIEW
|
RFQ Issue Date: August 1, 2013
Deadline for Quotations: 2:00 PM (Eastern), September 4, 2013
Question Submission: The deadline for submitting questions has passed.
No further questions will be accepted.
Project Summary:
The Contractor shall furnish all necessary labor, materials, tools, equipment and supervision for the installation of four point-to-point T-1 circuits in the offices supporting Phase 2 of the Dulles Corridor Metrorail Project.
DBE Goal:
None
Amendments Issued:
One, August 15, 2013.  The due date for quotations is extended from August 22, 2013 to August 29, 2013.
Two, August 27, 2013.  The due date for quotations is extended from August 29, 2013 to September 4, 2013.
CLICK HERE to download Amendment Documents
Last Updated August 27, 2013